1. How to manage distributed photovoltaic power generation projects?

A: The State Council’s energy authority is responsible for the national planning and supervision of distributed photovoltaic power generation planning; the local energy authority is responsible for the construction and supervision of distributed photovoltaic power generation projects in the region under the guidance of the State Council’s energy authority; entrusted with the national centralized management of solar power technology. The unit undertakes technical, information and engineering quality control work.

2. Why do distributed photovoltaic projects need to be filed? Can state-subsidized projects start construction?

A: At this stage, distributed photovoltaic power generation still needs state subsidies. It is assumed that 5GW of distributed photovoltaic power generation is installed each year. The annual power generation capacity is at least 6 billion kWh. If the subsidies are 0.42 yuan per kWh, it will need 2.52 billion yuan. In order to optimize the allocation of subsidy funds, filing is a must. Distributed photovoltaic power generation projects are managed by prefecture-level energy or county-level energy authorities. If the project does not require state subsidies, the project can be started immediately after the implementation of the record management.

3. How to prepare materials for distributed photovoltaic power generation projects?

A: The project unit submits the fixed assets investment filing form and the distributed photovoltaic power generation project filing application form to the provincial or county-level energy authorities. The following materials should be included:

1) Project plans that meet the relevant regulations for the installation of photovoltaic power generation systems in buildings and other facilities;

2) Proof of site use such as project land or roof;

3) Project and grid access opinions issued by the prefecture-level or county-level power grid companies;

4) If the project adopts contract energy management, it needs to provide energy service management contracts with electricity users and other materials

5) Other materials requested by the local government according to relevant regulations.

The municipal or county-level energy authority shall complete the record review within 10 working days after receiving the project filing application and inform the project entity of the review opinions. When the cumulative scale of the application projects exceeds the annual guidance scale of the area, the local energy authority Notices are issued to stop accepting applications for project filings. If there are no special reasons for the completion of the project, the project filing documents will automatically become invalid.

4. Can a registered project be able to apply for changes? How to change?

Registered projects can't be arbitrarily changed under normal circumstances. If there are special circumstances in the implementation of the project and the plan must be changed, the program must be changed according to the original reporting procedures.

5. How do individuals (households) install distributed PV systems? What are the preferential policies?

Encourage power users, investment companies, specialized contract energy service companies, and individuals to invest in and construct distributed photovoltaic power generation projects as project units.

The personally-installed distributed photovoltaic project shall, in principle, be used for its own use, with surplus electricity access to the grid, and the grid to adjust for deficits. For self-use of photovoltaic power, it will automatically offset the electricity consumption of the grid and will not conduct transactions. For the surplus grid-connected photovoltaic electricity grid company, the grid company purchases the local desulphurization coal benchmark price. Individual installation of a single photovoltaic power plant as a project unit The installed capacity of a single project is, in principle, not more than 30 kilowatts. The provincial energy administrations can simplify project management depending on the circumstances.